Overview

Home page
Level 4 1,240 XP 🔥 3 day streak
Your progress

Demo Construction Site

Mannerheimintie 10, Helsinki

3 of 5 tasks , 180 XP earned
Standard Apartment 4 apartments on project 1 buildings
Last clocked in
Jun 21, 2026
Month total
0 h
3
Completed
of 5 tasks
2
In progress
1
Apartments completed
of 2 worked
1
Apartments in progress

Active workflows

Tasks you started. Continue from scan or tap a card below.

Your apartments

Apartments where you have started or completed work.

Floor 1, Apartment 2

1/2

In Progress
Building A (a) Floor Floor 1
1 of 3 tasks 33%
1 Completed Completed
  • Kitchen cabinets mounted
2 In progress In progress
  • Countertop installed
  • Waterproofing completed
0 Not started

Floor 1, Apartment 1

1/1

Completed
Building A (a) Floor Floor 1 54.00 m²
2 of 2 tasks 100%
2 Completed Completed
  • Countertop installed
  • Kitchen cabinets mounted
0 In progress 0 Not started
No apartments on this floor yet.